Discussion Starter · #1 ·
Dear all,
I have included tasks in a project with theorethical starting dates.
Now if I go to tracking & I input the actual start, my bar representing the duration of my task on the GANTT chart will be shifted accordingly.

What i need to know is is there a way that i could see on my gantt chart both the original & actual bars one under the other so i can have a visual comparision of the shifting in my project after i correct by putting actual start values...

Thx
 

·
Registered
Joined
·
76 Posts
Discussion Starter · #2 ·
after TOOLS - TRACKING - SAVE BASELINE - ENTIRE PROJECT,
a set of grey bars identical to the original planned bars should appear but they aren't.
Even after VIEW-TABLE:ENTRY-MORE TABLE-BASELINE (ensuring that task is selected), I am unable to view these grey baseline which could answer my question if resolved.
 

·
Registered
Joined
·
76 Posts
Discussion Starter · #3 ·
ok, found it
the missing action was the following:
Right click on the Gantt chart - WIZARD -Baseline view...
 